tutorial 4



This is our Activity-On-Node(AON) chart with the forward and backward flow. Therefore, it is estimated that we are going to complete this project in about 32 weeks(8 months) and we will have a float of about 8 weeks.(2 months). Our Earliest Finish Time(EFT) will be 32 weeks and our Latest Finish Time will be 40weeks.

Lesson learnt: I learnt how to draw this AON chart. We must do it carefully. If anything were to calculate wrongly, the timing for everything will be wrong.